HKA assisted in the settlement of the claim out of court, in favour of the client, regarding the construction of the primary infrastructure of a business park.
The client had entered a design-and-build contract for the construction of primary infrastructure, including the business park spine road and drainage. At the commencement of the construction, it became clear that ground conditions were exceedingly poor and not as reflected in the initial site investigation.
Brief
The client had employed an engineer to provide engineering and project management services. This included a site investigation to determine soil conditions in preparation for the design. After the construction work had started, the site investigation was called into question as it emerged that the ground conditions were not as expected, requiring excessive excavation.
The poor-quality soil was disposed of off-site and replaced with imported granular material, resulting in increased cost and delay for the project.
HKA was appointed by the client to provide expert opinion on the adequacy of the initial site investigation and the quality of the interpretation of ground conditions.
What we did
Working closely with the client, HKA provided geotechnical engineering expert witness services in litigation delivering expert opinion on the sufficiency of the site investigation activities conducted by the original engineer.
The assessment included the independent analysis of the site investigation data and re-evaluation of whether this was accurately interpreted. It was found that the scope of the site investigation was adequate to accurately assess the ground conditions. However, the interpretation of the data was found to be inadequate, with the misinterpretation of the geology of the site and the engineering properties of the site soils.
Outcomes
The matter was settled out of court in favour of the client with HKA’s input cited as playing a significant role in securing this result for the client.
"I just wanted to add my own thanks for your considerable assistance with this claim. Your quick grasp of the circumstances at our initial meeting was both informative and reassuring and I have no doubt that your report and ongoing involvement in the case played a significant role in the Defendant’s finally putting forward some proposals for settlement."
Instructing solicitor
-
ClientConfidential
-
Year2022
-
ValueUSD$1million
-
ServicesForensic Engineering, Architectural and Technical, Expert
-
SectorsConstruction and Engineering, Transportation Infrastructure
RELATED PROJECTS
RELATED PROJECTS
Subsea Cable Installation & Trenching Operations
Asia
Independent Commercial, Cost & Risk Review of Road Development
Europe
Independent Quantum Expert Review of Maintenance Contract
Europe
Major Light Rail Transit
Americas
Two New Venues
Middle East
A Major Teaching & Research Hospital
Europe
Nuclear Power Plant
Americas
New School Campus, Ultimo Primary School
Oceania
UNSW Capital Projects Sustainability Framework
Oceania
Sydney Water, Partnering for Success (P4S)
Oceania
Melbourne Airport Rail
Oceania
Liquefied Natural Gas (LNG) Project Australia
Oceania
Residential Development
Middle East
Natural Gas-Fired Power Plant
Asia
Industrial Manufacturing Facility
Europe
Subsea Power Cable Failure
Asia
Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe
Subsea Interconnector Cable Failure
Europe
Energy and Telecom Cable Manufacturer
Americas & Asia
Franchise Fraudulent Transfer Matter
Americas
Clean Fuels Project
Middle East
Nuclear Power Plant Decommissioning
Americas
Global chemicals manufacturer
Americas & Europe
Home security company sale agreement
Americas
Highway Rock Cuttings
Middle East
Coal-fired power plant
Asia
Coal-fired power plant
Americas
Water desalination plant
Americas
Offshore refinery contractor performance review
Asia
WestConnex Rozelle Interchange
Oceania
Public transport service improvement
Oceania
Major Canadian Utility Commercial Damages Matter
Americas
Major Nuclear Power Plant
Americas
South American Oil Refinery
Americas
Power Plant
Americas
University of North Carolina Hospitals
Americas
Longview Power Plant
Americas
Spent Nuclear Fuel Verdicts & Settlements
Americas
Missouri Power Plant
Americas
Share our Space Program
Oceania
Lower South Creek Treatment Program
Oceania
Allseas & Pioneering Spirit
Europe
Hume Community Housing
Oceania
Infrastructure Investment Assurance Framework
Oceania
Electricity Network Improvement
Oceania
Major Transport Projects Review
Oceania
High Speed 2 (HS2) Project
Europe
Urban Transformation & Transport Programme
Oceania
Strategic Procurement & Programme Management Improvement
Oceania
Business Reform & Procurement Strategy
Australia
Sydney Metro
Oceania
Temporary School at Ultimo Primary School
Oceania
Gerald Desmond Bridge
Americas
Office and Retail Landmark
Americas
Port of Long Beach
Americas
Airport Pavement Management Survey
Americas
Greenfield St George Airport, Utah
Americas
A Giant Oilfield
Asia
Hunter River Remediation
New South Wales, Australia
Great Western Highway Widening
Victoria, Australia
Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania
Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号