Brief
Awarded a lump-sum contract, the building services subcontractor was incurring significant unbudgeted costs. Despite delays in completing the design and civil works, the main contractor, who had full design responsibility, had rejected the subcontractor’s claims.
HKA was commissioned to undertake an initial review and prepare a strategy to maximise the commercial position of the MEP subcontractor. We were subsequently appointed to prepare a series of claims for extension of time, delay and disruption related costs and variations.
What we did
HKA assembled a multidisciplinary team, drawing on our QED+ (quantum, engineering, delay) capability.
Our initial review clearly established that failures by the main contractor in its design obligations and allowing access for the MEP works had caused the client critical delays. Significant design changes had also resulted in additional costs.
We advised on the need for more detailed progress updates and daily site records, and devised a strategy that, nevertheless, would provide a strong basis for recovering costs. This included a potential claim for constructive acceleration as well as for design variations, extension of time, and delay and disruption related costs.
In stage two, our team – which comprised five quantum specialists, two engineers and two delay analysts – prepared these claims.
- Variations: A structured workshop with the site team identified time-critical design variations. We reviewed the subcontractor’s previous submissions, carried out our own technical analysis to define the scope of works based on the original design documents, and mapped the extent of the design changes.
Detailed and persuasive claims for each major variation were then prepared. These were extensive, amounting to around a hundred claims.
- Extension of time: Our ‘as-planned versus as-built’ methodology provided the basis for a solid delay analysis backed up with a detailed narrative of logic and findings. When updating the claim, the subsequent period was subjected to a ‘time slice’ retrospective analysis.
We also reviewed the contract to assemble the strongest possible case for the recovery of time and costs arising from each delay event.
- Additional claims: Our team carried out all the necessary assessments to establish entitlement to other costs arising from prolongation, disruption/lost productivity, constructive acceleration (to meet an imposed completion date), and related losses.
The impact of disruption was calculated on an earned value basis. As when updating the EOT claim, with more detailed records available, we could deploy a ‘measured mile’ methodology for the later period. This was then applied retrospectively to supersede the initial claim.
Outcomes
Our integrated QED+ capability was critical both in securing the commission and the subcontractor’s commercial position.
The HKA team safeguarded the rights of our client ahead of arbitration. Our advice on record keeping and subsequent analysis strengthened its claims, which have been prepared to the most rigorous standards possible. Their total value exceeded that of the subcontract.
"Our integrated QED+ capability was critical both in securing the commission and the subcontractor’s commercial position."
-
ClientConfidential
-
Year2018 - 2020
-
ServicesForensic Engineering, Architectural and Technical, Expert, Engineering and Construction Quantum, Delay and Disruption Analysis
-
SectorsConstruction and Engineering, Buildings
RELATED PROJECTS
RELATED PROJECTS
Subsea Interconnector Cable Failure
Europe
Independent Commercial, Cost & Risk Review of Road Development
Europe
Independent Quantum Expert Review of Maintenance Contract
Europe
Major Light Rail Transit
Americas
A Major Teaching & Research Hospital
Europe
Nuclear Power Plant
Americas
New School Campus, Ultimo Primary School
Oceania
UNSW Capital Projects Sustainability Framework
Oceania
Sydney Water, Partnering for Success (P4S)
Oceania
Melbourne Airport Rail
Oceania
Liquefied Natural Gas (LNG) Project Australia
Oceania
Residential Development
Middle East
Natural Gas-Fired Power Plant
Asia
Industrial Manufacturing Facility
Europe
Subsea Power Cable Failure
Asia
Subsea Cable Installation & Trenching Operations
Asia
Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe
Energy and Telecom Cable Manufacturer
Americas & Asia
Franchise Fraudulent Transfer Matter
Americas
Clean Fuels Project
Middle East
Nuclear Power Plant Decommissioning
Americas
Global chemicals manufacturer
Americas & Europe
Home security company sale agreement
Americas
Business Park, Surrey
Europe
Highway Rock Cuttings
Middle East
Coal-fired power plant
Asia
Coal-fired power plant
Americas
Water desalination plant
Americas
Offshore refinery contractor performance review
Asia
WestConnex Rozelle Interchange
Oceania
Public transport service improvement
Oceania
Major Canadian Utility Commercial Damages Matter
Americas
Major Nuclear Power Plant
Americas
South American Oil Refinery
Americas
Power Plant
Americas
University of North Carolina Hospitals
Americas
Longview Power Plant
Americas
Spent Nuclear Fuel Verdicts & Settlements
Americas
Missouri Power Plant
Americas
Share our Space Program
Oceania
Lower South Creek Treatment Program
Oceania
Allseas & Pioneering Spirit
Europe
Hume Community Housing
Oceania
Infrastructure Investment Assurance Framework
Oceania
Electricity Network Improvement
Oceania
Major Transport Projects Review
Oceania
High Speed 2 (HS2) Project
Europe
Urban Transformation & Transport Programme
Oceania
Strategic Procurement & Programme Management Improvement
Oceania
Business Reform & Procurement Strategy
Australia
Sydney Metro
Oceania
Temporary School at Ultimo Primary School
Oceania
Gerald Desmond Bridge
Americas
Office and Retail Landmark
Americas
Port of Long Beach
Americas
Airport Pavement Management Survey
Americas
Greenfield St George Airport, Utah
Americas
A Giant Oilfield
Asia
Hunter River Remediation
New South Wales, Australia
Great Western Highway Widening
Victoria, Australia
Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania
Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号