HKA was key to Nuclear Power Companies’ efforts to recover US$1.8 billion from U.S. Government in pivotal spent nuclear fuel verdicts and settlements
Brief
In 1982, the Nuclear Waste Policy Act (NWPA) was enacted to regulate the disposal of nuclear waste. Under the Act, the Nuclear Waste Fund was established to finance the research, construction and maintenance of nuclear waste repositories, as well as the safe transport of the waste from the nuclear plants to a permanent storage facility. Nuclear power companies were required to pick up the tab – together paying nearly US$800 million into the fund annually – with the understanding that disposal would commence in 1998. It did not – in part due to the political turmoil that ultimately erupted over the proposed disposal site: Yucca Mountain, Nevada.
Having acted under the assumption that DOE would honor its contractual agreement, power companies were now left to properly handle waste that would require them to incur tens to hundreds of millions of dollars to build their own spent nuclear fuel storage facilities at each of their reactor sites, and obtain the requisite approval of local and state government officials to store that waste.
Most US nuclear plants began operations in the 1970s and early 1980s. The earliest of these plants were generally built to accommodate the storage of spent fuel for just a few years until such time that the Government took the fuel for “reprocessing”. Following President Carter’s effective ban on reprocessing due to proliferation concerns, the NWPA-mandated contracts would require each nuclear utility to find a means to store its spent fuel on its nuclear plant site until DOE began to accept spent fuel in 1998.
While the NWPA and related DOE contracts with nuclear utilities explicitly identified 1998 as the date when DOE would begin accepting spent fuel from nuclear plants, the rate of acceptance and the specifics with which such acceptance would occur were not as clearly specified.
What we did
Retained by outside counsel for many of the nuclear utilities, HKA performed extensive fact-finding. This was done by conducting interviews of company executives, plant managers, operators and other technical specialists, and reviewing operational and accounting records, often dating back to the early 1980s.
Based on this investigation, the HKA team performed in-depth analyses to quantify the incremental amount of spent fuel that would be stored onsite at each nuclear plant and the resulting cost impacts. For each case, HKA prepared expert damages reports. The supporting evidence typically amounted to thousands of pages of documents and analyses.
HKA experts then delivered clear and concise expert testimony to explain to the court the basis of the plaintiffs’ damages.
Outcomes
HKA expert witnesses were able to demonstrate to the courts the substantial economic damages the power companies had borne to date and will continue to bear because of DOE’s failure to perform on its contractual obligations.
The damage awards in HKA matters have totalled more than 90% of the claim amounts.
Of the resolved cases, the awards encompassed the overwhelming majority of the elements of damages that HKA had determined. Several of these plaintiffs have pursued subsequent rounds of litigation to recover their ongoing costs.
- In July 2007, a gas and electric utility company was awarded approximately US$77 million in damages by the US Court of Federal Claims for its three power plants located in Georgia and Alabama.
- In September 2007, a publicly-traded electric and natural gas utility company was awarded approximately US$116 million in a ruling by the US Court of Federal Claims for its Prairie Island and Monticello nuclear plants for costs incurred through 2004. In July 2011, the company settled its claim with the Department of Justice for approximately US$100 million for costs incurred through 2008.
- In October 2007, a fortune 500 energy company was awarded approximately US$49 million in damages by the US Court of Federal Claims for its Arkansas nuclear power plant.
- In December 2009, an electricity and natural gas company was awarded approximately US$50 million in damages by the US Court of Federal Claims for the Point Beach nuclear plant. In February 2011, the company settled the claim with the Department of Justice for US$46 million.
- In February 2010, a public power joint operating agency was awarded approximately US$57 million in damages by the US Court of Federal Claims for its Columbia nuclear plant. In July 2011, the agency settled the claim with the Department of Justice for US$49 million.
- In March 2010, a fortune 500 integrated energy company was awarded approximately US$10 million in damages by the US Court of Federal Claims for its Grand Gulf nuclear power plant in Mississippi.
- In May 2010, a fortune 500 integrated energy company was awarded approximately US$4 million in damages by the US Court of Federal Claims for its Pilgrim nuclear plant.
- In May 2010, a fortune 500 integrated energy company was awarded approximately US$106 million in damages by the US Court of Federal Claims for its Indian Point nuclear plant.
HKA’s work was cited numerous times in court decisions in making the case against the US government.
In addition to the work done on litigations, HKA also assisted several utilities in settlements with the Department of Justice. We continue to assist many of these utilities on annual settlement submissions provided to the DOE. These annual submissions cover the utilities’ ongoing costs for addressing spent nuclear fuel until the time DOE performs.
- In January 2006, a power and energy company was awarded US$6 million in a settlement agreement with the Department of Justice.
- In June 2006, a public electric utility company was awarded US$15 million in a settlement agreement with the Department of Justice.
- In March 2007, an electric power and natural gas company was awarded US$56 million for its nuclear plants in a settlement agreement with the Department of Justice.
- In mid-2009, a power utility company was awarded a confidential amount in a settlement agreement with the Department of Justice.
- In September 2009, an energy company was awarded US$47 million in a settlement agreement with the Department of Justice.
- In March 2011, an energy company was awarded US$55 million in a settlement agreement with the Department of Justice.
- In May 2011, an electric utility company was awarded US$61 million in a settlement agreement with the Department of Justice
By industry estimates, the total damages to be paid by DOE could be in the tens of billions of dollars.
For HKA clients still awaiting resolution, the precedent set by the utility companies’ wins offers significant hope that at least the utilities and their ratepayers will not ultimately have to pay twice to address the issue of spent nuclear fuel.

-
ClientVarious
-
ValueUS$900 million
-
ServicesCommercial Damages and Valuation, Economic Damages, Expert
-
SectorsConstruction and Engineering, Government Contracts, Power and Utilities
RELATED PROJECTS
RELATED PROJECTS

Nuclear Power Plant
Americas

Industrial Manufacturing Facility
Europe

Natural Gas-Fired Power Plant
Asia

Residential Development
Middle East

Liquefied Natural Gas (LNG) Project Australia
Oceania

Melbourne Airport Rail
Oceania

Sydney Water, Partnering for Success (P4S)
Oceania

UNSW Capital Projects Sustainability Framework
Oceania

New School Campus, Ultimo Primary School
Oceania

Subsea Power Cable Failure
Asia

DCAA Audit Issues
Americas

Contracting and Grant Compliance
Americas

Bid Protest
Americas

Pricing and Billing Investigation
Americas

Trade Secret and Prime-Sub Damages
Americas

A Major Teaching & Research Hospital
Europe

Two New Venues
Middle East

Major Light Rail Transit
Americas

Home security company sale agreement
Americas

Public transport service improvement
Oceania

WestConnex Rozelle Interchange
Oceania

Offshore refinery contractor performance review
Asia

Water desalination plant
Americas

Coal-fired power plant
Americas

Coal-fired power plant
Asia

Highway Rock Cuttings
Middle East

Business Park, Surrey
Europe

Independent Quantum Expert Review of Maintenance Contract
Europe

Fraudulent billing for security services
Americas & Asia

Global chemicals manufacturer
Americas & Europe

Nuclear Power Plant Decommissioning
Americas

Clean Fuels Project
Middle East

Franchise Fraudulent Transfer Matter
Americas

Energy and Telecom Cable Manufacturer
Americas & Asia

Subsea Interconnector Cable Failure
Europe

Subsea Cable Installation & Trenching Operations
Asia

Independent Commercial, Cost & Risk Review of Road Development
Europe

Missouri Power Plant
Americas

Longview Power Plant
Americas

University of North Carolina Hospitals
Americas

Power Plant
Americas

Future Combat Systems Program
Americas

T-45A Aircraft
Americas

Logistics Modernization Program
Americas

South American Oil Refinery
Americas

Major Nuclear Power Plant
Americas

Major Canadian Utility Commercial Damages Matter
Americas

Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe

Share our Space Program
Oceania

Lower South Creek Treatment Program
Oceania

Allseas & Pioneering Spirit
Europe

Hume Community Housing
Oceania

Infrastructure Investment Assurance Framework
Oceania

Electricity Network Improvement
Oceania

Major Transport Projects Review
Oceania

High Speed 2 (HS2) Project
Europe

Urban Transformation & Transport Programme
Oceania

Strategic Procurement & Programme Management Improvement
Oceania

Business Reform & Procurement Strategy
Australia

Sydney Metro
Oceania

Temporary School at Ultimo Primary School
Oceania

Gerald Desmond Bridge
Americas

Office and Retail Landmark
Americas

Port of Long Beach
Americas

Airport Pavement Management Survey
Americas

Greenfield St George Airport, Utah
Americas

A Giant Oilfield
Asia

Hunter River Remediation
New South Wales, Australia

Great Western Highway Widening
Victoria, Australia

Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania

Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号
