The Joint Venture (JV) Contractor was engaged under an Engineering, Procurement and Construction (EPC) contract to revamp existing facilities and install new units on behalf of the refinery Employer.
Brief
The JV Contractor sought an adjustment of the contractual completion date and financial compensation due to delays in purchase order placement, discovery of unexpected underground obstacles, delay in manpower mobilisation and time-consuming procedures for access to site. Heavy rain and subsequent flooding caused serious damage to the greenfield area of the site causing the JV Contractor to require both a geotechnical engineering expert and an insurance coordinator to advise on the extent of the damage and on the remediation measures that the JV Contractor should adopt, as well as to advise and lead the preparation of the claim to the insurers.
What we did
The HKA team comprised three quantum experts, two delay experts, one planning consultant, one geotechnical expert and one insurance expert, mobilised from our network of offices worldwide.
The team initially carried out a comprehensive review of the available documentation relating to the JV Contractor’s first submitted Extension of Time (EOT) claim and subsequently, working alongside the JV Contractor’s team, prepared a revised, robust EOT claim. The revised EOT claim consisted of contractual entitlement, identification and justification of delays not attributable to the JV Contractor, an in-depth analysis of the delays and a quantum analysis of the delay and disruption. HKA also supported the JV Contractor in the EOT negotiations with the Employer.
Following the heavy rains, the geotechnical expert visited the site to inspect and record visible damage, assess subterranean damage and review on-site records. A desk study appraisal was carried out where the expert reviewed all available contractual, hydrological and project documents in order to formulate detailed guidance on the design and implementation of the preferred ground and drainage remediation options. Working alongside the rest of the HKA team, the insurance coordinator assisted the JV Contractor to prepare the insurance claim for the ground remediation works, and any associated costs arising from the flood, as well as prepared draft correspondence to both the Employer and the Insurer.
Outcomes
Our findings on quantum, engineering and delay confirmed that a robust case based on further detailed evidence needed to be constructed. The client and its legal advisors appreciated the value that our joint approach added to the JV Contractor’s case and claim and were confident they had achieved greater clarity on their position. The integrated QED (Quantum, Engineering and Delay) approach that was applied by the HKA team of experts was vital towards building a strong case to support the client’s claim.

"The integrated QED (Quantum, Engineering and Delay) approach that was applied by the HKA team of experts was vital towards building a strong case to support the client’s claim."
-
ClientConfidential
-
Valuec. €40 million
-
ServicesForensic Engineering, Architectural and Technical, Expert, Engineering and Construction Quantum, Delay and Disruption Analysis
-
SectorsConstruction and Engineering, Power and Utilities
RELATED PROJECTS
RELATED PROJECTS

Subsea Cable Installation & Trenching Operations
Asia

Independent Commercial, Cost & Risk Review of Road Development
Europe

Independent Quantum Expert Review of Maintenance Contract
Europe

Major Light Rail Transit
Americas

Two New Venues
Middle East

A Major Teaching & Research Hospital
Europe

Nuclear Power Plant
Americas

New School Campus, Ultimo Primary School
Oceania

UNSW Capital Projects Sustainability Framework
Oceania

Sydney Water, Partnering for Success (P4S)
Oceania

Melbourne Airport Rail
Oceania

Liquefied Natural Gas (LNG) Project Australia
Oceania

Residential Development
Middle East

Natural Gas-Fired Power Plant
Asia

Industrial Manufacturing Facility
Europe

Subsea Power Cable Failure
Asia

Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe

Subsea Interconnector Cable Failure
Europe

Energy and Telecom Cable Manufacturer
Americas & Asia

Franchise Fraudulent Transfer Matter
Americas

Nuclear Power Plant Decommissioning
Americas

Global chemicals manufacturer
Americas & Europe

Home security company sale agreement
Americas

Business Park, Surrey
Europe

Highway Rock Cuttings
Middle East

Coal-fired power plant
Asia

Coal-fired power plant
Americas

Water desalination plant
Americas

Offshore refinery contractor performance review
Asia

WestConnex Rozelle Interchange
Oceania

Public transport service improvement
Oceania

Major Canadian Utility Commercial Damages Matter
Americas

Major Nuclear Power Plant
Americas

South American Oil Refinery
Americas

Power Plant
Americas

University of North Carolina Hospitals
Americas

Longview Power Plant
Americas

Spent Nuclear Fuel Verdicts & Settlements
Americas

Missouri Power Plant
Americas

Share our Space Program
Oceania

Lower South Creek Treatment Program
Oceania

Allseas & Pioneering Spirit
Europe

Hume Community Housing
Oceania

Infrastructure Investment Assurance Framework
Oceania

Electricity Network Improvement
Oceania

Major Transport Projects Review
Oceania

High Speed 2 (HS2) Project
Europe

Urban Transformation & Transport Programme
Oceania

Strategic Procurement & Programme Management Improvement
Oceania

Business Reform & Procurement Strategy
Australia

Sydney Metro
Oceania

Temporary School at Ultimo Primary School
Oceania

Gerald Desmond Bridge
Americas

Office and Retail Landmark
Americas

Port of Long Beach
Americas

Airport Pavement Management Survey
Americas

Greenfield St George Airport, Utah
Americas

A Giant Oilfield
Asia

Hunter River Remediation
New South Wales, Australia

Great Western Highway Widening
Victoria, Australia

Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania

Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号