This manufacturing and industrial project ran into serious difficulties, which resulted in significant delay and cost escalation.
Brief
HKA was retained by the client to assess the performance of the contractor and to provide an independent expert opinion on the reasons for the cost and schedule overruns and the resulting operational losses.
What we did
The complexity of the project demanded an integrated multidisciplinary approach to establish how the contractor’s actions, or omissions, affected the outturn costs and overrun. The HKA team comprised experts in project delivery, process engineering, civil engineering, 3D modelling, delay and quantum, and a specialist in assessing losses and damages. This analysis involved:
- Using our own unique methods of analysis to forensically interrogate the available data including HKA Advanced Project Performance Analytics (APPA) to identify and understand the issues and causation affecting progress at each stage of the programme.
- Innovative use of specialist software to analyse the changes within the 3D model.
- Mining project records to develop a factually based as-built schedule and identifying critical impacts on the planned programme.
- Assessing manpower levels on site and how they changed as engineering problems were encountered.
- Identifying the true causes and quantifying the increases to project costs and schedule delays.
- Quantifying the impact of delayed completion on the manufacturer’s operational costs and lost profits.
- Mapping the evolution of the scope and detailed design and then correlating this to the corresponding changes to the 3D model. The change control records were a crucial strand of the investigation to determine the underlying reasons and the impact of those changes.
Outcomes
Our client gained an independent, expert perspective on the project and how it was executed. By combining complementary skills in a multi-faceted and integrated analysis, we were able to decode a highly complex project and construct an alternative, evidence-based assessment of the project delivery. This will provide the basis for a negotiated settlement or the detailed analysis required to support litigation.

"HKA was retained by the client to assess the performance of the contractor and to provide an independent expert opinion on the reasons for the cost and schedule overruns and the resulting operational losses."
-
ClientConfidential
-
Value€100 million
-
ServicesForensic Engineering, Architectural and Technical, Commercial Damages and Valuation, Economic Damages, Expert, Engineering and Construction Quantum, Delay and Disruption Analysis
-
SectorsConstruction and Engineering, Industrial and Manufacturing
RELATED PROJECTS
RELATED PROJECTS

Subsea Interconnector Cable Failure
Europe

Independent Commercial, Cost & Risk Review of Road Development
Europe

Independent Quantum Expert Review of Maintenance Contract
Europe

Major Light Rail Transit
Americas

Two New Venues
Middle East

A Major Teaching & Research Hospital
Europe

Nuclear Power Plant
Americas

New School Campus, Ultimo Primary School
Oceania

UNSW Capital Projects Sustainability Framework
Oceania

Sydney Water, Partnering for Success (P4S)
Oceania

Melbourne Airport Rail
Oceania

Liquefied Natural Gas (LNG) Project Australia
Oceania

Residential Development
Middle East

Natural Gas-Fired Power Plant
Asia

Subsea Power Cable Failure
Asia

Subsea Cable Installation & Trenching Operations
Asia

Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe

Energy and Telecom Cable Manufacturer
Americas & Asia

Franchise Fraudulent Transfer Matter
Americas

Clean Fuels Project
Middle East

Nuclear Power Plant Decommissioning
Americas

Global chemicals manufacturer
Americas & Europe

Home security company sale agreement
Americas

Business Park, Surrey
Europe

Highway Rock Cuttings
Middle East

Coal-fired power plant
Asia

Coal-fired power plant
Americas

Water desalination plant
Americas

Offshore refinery contractor performance review
Asia

WestConnex Rozelle Interchange
Oceania

Public transport service improvement
Oceania

Major Canadian Utility Commercial Damages Matter
Americas

Major Nuclear Power Plant
Americas

South American Oil Refinery
Americas

Power Plant
Americas

University of North Carolina Hospitals
Americas

Longview Power Plant
Americas

Spent Nuclear Fuel Verdicts & Settlements
Americas

Missouri Power Plant
Americas

Share our Space Program
Oceania

Lower South Creek Treatment Program
Oceania

Allseas & Pioneering Spirit
Europe

Hume Community Housing
Oceania

Infrastructure Investment Assurance Framework
Oceania

Electricity Network Improvement
Oceania

Major Transport Projects Review
Oceania

High Speed 2 (HS2) Project
Europe

Urban Transformation & Transport Programme
Oceania

Strategic Procurement & Programme Management Improvement
Oceania

Business Reform & Procurement Strategy
Australia

Sydney Metro
Oceania

Temporary School at Ultimo Primary School
Oceania

Gerald Desmond Bridge
Americas

Office and Retail Landmark
Americas

Port of Long Beach
Americas

Airport Pavement Management Survey
Americas

Greenfield St George Airport, Utah
Americas

A Giant Oilfield
Asia

Hunter River Remediation
New South Wales, Australia

Great Western Highway Widening
Victoria, Australia

Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania

Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号