HKA assists contractor in recovering approximately 95% of damages sought in jury trial
Brief
A leading contractor in the construction industry was employed by a multinational manufacturer to perform civil construction activities on a four-unit nuclear power plant in California. The original contract was valued at US$45 million and grew to US$70 million through approved change orders by the manufacturing firm.
The contractor submitted an extra US$25 million in change orders and incurred additional costs for delay, disruption, and acceleration of the project not captured in change orders. No extension was granted to the contractor even though the contract price doubled. The contractor sought to recover both damages from the manufacturing firm for its excess construction costs and the $25 million in unpaid change orders.
What we did
HKA was retained by the contractor prior to trial to determine the parties responsible for the project delays and excess costs. Our analysis of project schedules and documents showed that the project delays were not the contractor’s responsibility. The manufacturing firm did not provide the contractor with any schedule relief, despite a revised project schedule that was impacted by numerous changes from the original design.
HKA pointed to several key issues to help prove the contractor’s case. We also found that the manufacturing firm responsible for the project design was late in providing significant design information to the contractor. Our analysis was presented at several mediation sessions but ultimately did not prevent this matter from going to trial.
During trial proceedings, HKA experts testified about their findings in a manner that was geared toward making the issues readily understandable to a jury. This testimony helped the jury determine the party at fault by clarifying the key concepts and facts involved in the construction and schedule analysis. Our succinct and focused testimony greatly contrasted with that of the manufacturing firm’s schedule expert.
Outcomes
The jury agreed with the assessment made by HKA, resulting in the contractor recovering approximately 95% of the damages sought. The contractor was awarded nearly US$32 million of the approximately US$34 million in damages sought from the manufacturing firm. Additionally, the contractor defeated all claims and counterclaims presented by the manufacturing firm for liquidated damages and delays. The manufacturing firm’s counterclaims totaling approximately US$40 million were valued at US$0 by the jury.
HKA’s detailed work and expert testimony at trial directly impacted the favorable outcome for the contractor. Our experts’ extensive knowledge and experience enabled them to concisely present schedule analysis during trial that educated the jury about the facts surrounding their conclusions. HKA ultimately proved that the manufacturing firm was responsible for the major delays to the project as well as all contractor delays and increased costs.

"HKA’s detailed work and expert testimony at trial directly impacted the favorable outcome for the contractor."
-
ClientContractor
-
ValueUS$45 million
-
ServicesExpert, Engineering and Construction Quantum, Delay and Disruption Analysis
-
SectorsConstruction and Engineering, Power and Utilities
RELATED PROJECTS
RELATED PROJECTS

Subsea Interconnector Cable Failure
Europe

Independent Commercial, Cost & Risk Review of Road Development
Europe

Independent Quantum Expert Review of Maintenance Contract
Europe

Major Light Rail Transit
Americas

Two New Venues
Middle East

A Major Teaching & Research Hospital
Europe

New School Campus, Ultimo Primary School
Oceania

UNSW Capital Projects Sustainability Framework
Oceania

Sydney Water, Partnering for Success (P4S)
Oceania

Melbourne Airport Rail
Oceania

Liquefied Natural Gas (LNG) Project Australia
Oceania

Residential Development
Middle East

Natural Gas-Fired Power Plant
Asia

Industrial Manufacturing Facility
Europe

Subsea Power Cable Failure
Asia

Subsea Cable Installation & Trenching Operations
Asia

Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe

Energy and Telecom Cable Manufacturer
Americas & Asia

Franchise Fraudulent Transfer Matter
Americas

Clean Fuels Project
Middle East

Nuclear Power Plant Decommissioning
Americas

Global chemicals manufacturer
Americas & Europe

Home security company sale agreement
Americas

Business Park, Surrey
Europe

Highway Rock Cuttings
Middle East

Coal-fired power plant
Asia

Coal-fired power plant
Americas

Water desalination plant
Americas

Offshore refinery contractor performance review
Asia

WestConnex Rozelle Interchange
Oceania

Public transport service improvement
Oceania

Major Canadian Utility Commercial Damages Matter
Americas

Major Nuclear Power Plant
Americas

South American Oil Refinery
Americas

Power Plant
Americas

University of North Carolina Hospitals
Americas

Longview Power Plant
Americas

Spent Nuclear Fuel Verdicts & Settlements
Americas

Missouri Power Plant
Americas

Share our Space Program
Oceania

Lower South Creek Treatment Program
Oceania

Allseas & Pioneering Spirit
Europe

Hume Community Housing
Oceania

Infrastructure Investment Assurance Framework
Oceania

Electricity Network Improvement
Oceania

Major Transport Projects Review
Oceania

High Speed 2 (HS2) Project
Europe

Urban Transformation & Transport Programme
Oceania

Strategic Procurement & Programme Management Improvement
Oceania

Business Reform & Procurement Strategy
Australia

Sydney Metro
Oceania

Temporary School at Ultimo Primary School
Oceania

Gerald Desmond Bridge
Americas

Office and Retail Landmark
Americas

Port of Long Beach
Americas

Airport Pavement Management Survey
Americas

Greenfield St George Airport, Utah
Americas

A Giant Oilfield
Asia

Hunter River Remediation
New South Wales, Australia

Great Western Highway Widening
Victoria, Australia

Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania

Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号