HKA assists contractor in recovering approximately 95% of damages sought in jury trial
Brief
A leading contractor in the construction industry was employed by a multinational manufacturer to perform civil construction activities on a four-unit nuclear power plant in California. The original contract was valued at US$45 million and grew to US$70 million through approved change orders by the manufacturing firm.
The contractor submitted an extra US$25 million in change orders and incurred additional costs for delay, disruption, and acceleration of the project not captured in change orders. No extension was granted to the contractor even though the contract price doubled. The contractor sought to recover both damages from the manufacturing firm for its excess construction costs and the $25 million in unpaid change orders.
What we did
HKA was retained by the contractor prior to trial to determine the parties responsible for the project delays and excess costs. Our analysis of project schedules and documents showed that the project delays were not the contractor’s responsibility. The manufacturing firm did not provide the contractor with any schedule relief, despite a revised project schedule that was impacted by numerous changes from the original design.
HKA pointed to several key issues to help prove the contractor’s case. We also found that the manufacturing firm responsible for the project design was late in providing significant design information to the contractor. Our analysis was presented at several mediation sessions but ultimately did not prevent this matter from going to trial.
During trial proceedings, HKA experts testified about their findings in a manner that was geared toward making the issues readily understandable to a jury. This testimony helped the jury determine the party at fault by clarifying the key concepts and facts involved in the construction and schedule analysis. Our succinct and focused testimony greatly contrasted with that of the manufacturing firm’s schedule expert.
Outcomes
The jury agreed with the assessment made by HKA, resulting in the contractor recovering approximately 95% of the damages sought. The contractor was awarded nearly US$32 million of the approximately US$34 million in damages sought from the manufacturing firm. Additionally, the contractor defeated all claims and counterclaims presented by the manufacturing firm for liquidated damages and delays. The manufacturing firm’s counterclaims totaling approximately US$40 million were valued at US$0 by the jury.
HKA’s detailed work and expert testimony at trial directly impacted the favorable outcome for the contractor. Our experts’ extensive knowledge and experience enabled them to concisely present schedule analysis during trial that educated the jury about the facts surrounding their conclusions. HKA ultimately proved that the manufacturing firm was responsible for the major delays to the project as well as all contractor delays and increased costs.
"HKA’s detailed work and expert testimony at trial directly impacted the favorable outcome for the contractor."
-
ClientContractor
-
ValueUS$45 million
-
ServicesExpert, Engineering and Construction Quantum, Delay and Disruption Analysis
-
SectorsConstruction and Engineering, Power and Utilities
RELATED PROJECTS
RELATED PROJECTS
Subsea Interconnector Cable Failure
Europe
Independent Commercial, Cost & Risk Review of Road Development
Europe
Independent Quantum Expert Review of Maintenance Contract
Europe
Major Light Rail Transit
Americas
Two New Venues
Middle East
A Major Teaching & Research Hospital
Europe
New School Campus, Ultimo Primary School
Oceania
UNSW Capital Projects Sustainability Framework
Oceania
Sydney Water, Partnering for Success (P4S)
Oceania
Melbourne Airport Rail
Oceania
Liquefied Natural Gas (LNG) Project Australia
Oceania
Residential Development
Middle East
Natural Gas-Fired Power Plant
Asia
Industrial Manufacturing Facility
Europe
Subsea Power Cable Failure
Asia
Subsea Cable Installation & Trenching Operations
Asia
Independent Quantum Expert Opinion of Highway Maintenance Contract
Europe
Energy and Telecom Cable Manufacturer
Americas & Asia
Franchise Fraudulent Transfer Matter
Americas
Clean Fuels Project
Middle East
Nuclear Power Plant Decommissioning
Americas
Global chemicals manufacturer
Americas & Europe
Home security company sale agreement
Americas
Business Park, Surrey
Europe
Highway Rock Cuttings
Middle East
Coal-fired power plant
Asia
Coal-fired power plant
Americas
Water desalination plant
Americas
Offshore refinery contractor performance review
Asia
WestConnex Rozelle Interchange
Oceania
Public transport service improvement
Oceania
Major Canadian Utility Commercial Damages Matter
Americas
Major Nuclear Power Plant
Americas
South American Oil Refinery
Americas
Power Plant
Americas
University of North Carolina Hospitals
Americas
Longview Power Plant
Americas
Spent Nuclear Fuel Verdicts & Settlements
Americas
Missouri Power Plant
Americas
Share our Space Program
Oceania
Lower South Creek Treatment Program
Oceania
Allseas & Pioneering Spirit
Europe
Hume Community Housing
Oceania
Infrastructure Investment Assurance Framework
Oceania
Electricity Network Improvement
Oceania
Major Transport Projects Review
Oceania
High Speed 2 (HS2) Project
Europe
Urban Transformation & Transport Programme
Oceania
Strategic Procurement & Programme Management Improvement
Oceania
Business Reform & Procurement Strategy
Australia
Sydney Metro
Oceania
Temporary School at Ultimo Primary School
Oceania
Gerald Desmond Bridge
Americas
Office and Retail Landmark
Americas
Port of Long Beach
Americas
Airport Pavement Management Survey
Americas
Greenfield St George Airport, Utah
Americas
A Giant Oilfield
Asia
Hunter River Remediation
New South Wales, Australia
Great Western Highway Widening
Victoria, Australia
Rail Rehabilitation Scheme
Bucharest to Brasov line, Romania
Yanbu Power & Desalination Plant
Yanbu Industrial City, Saudi Arabia
Follow HKA on WeChat
关注我们的官方微信公众号